Question of the Day #372

 

372.Project communications management includes the processes employed to ensure punctual and appropriate creation, collection, distribution, storage, retrieval and final archiving of project information. All of the following are the processes of communications management EXCEPT?

 


1. Build stakeholder

2. Communications planning

3. Information distribution

4. Performance reporting



 

 



 

 

 

 

 

 

 

 

 

 

 


Answer and Explanation to Yesterday's Question


Answer :
1.
Performance measurement baseline
-----------------------------------------------------------------------------------------------------------------------------

Question Explanation:

You can use performance reports to organize and summarize collected information, and then present the results of the analysis in comparison to the performance measurement baseline.

 

 

 

Source of Answer : PMBOK Guide,3rd, pages : 232-233

 