Question of the Day #369

 

369. Your project has several problems. The schedule performance index (SPI) is 0.72, the cost performance index (CPI) is 1.02, and there are over 23 unexecuted critical activities. In a monthly status review meeting, what should you report?

 


1. Report the project's problems and suggest ways to deal with them.

2. Report the project's problems and suggest ways to deal with them.

3. Report the project's problems and suggest ways to deal with them.

4. Report that the project is progressing well.



 

 



 

 

 

 

 

 

 

 

 

 

 


Answer and Explanation to Yesterday's Question


Answer :
1. Histogram

-----------------------------------------------------------------------------------------------------------------------------

Question Explanation :

Common formats for performance report include bar charts, S-curves, histograms and tables.

 

 

 

 

 

 

Source of Answer : PMBOK Guide,3rd, pages : 233-234

 