Question of the Day #354

 

354. A control chart of production displays all the last 10 sports shots weighing below the average, and you have to inform senior management of this because which rule has been broken?


1. Rule of seven

2. Rule of ten

3. Mean

4. 6-sigma



 

 



 

 

 

 

 

 

 

 

 

 

 


Answer and Explanation to Yesterday's Question


Answer :
1. Process analysis


-----------------------------------------------------------------------------------------------------------------------------

Question Explanation :

The tools and techniques for quality planning include: cost-benefit analysis, benchmarking, design of experiments, cost of quality and additional quality planning tools. Process analysis is a tool for performing quality assurance.

 

 

Source of Answer : PMBOK Guide,3rd, pages : 184

 