of the Day #333
333. You are the project manager on a construction project for a water tower. Because of the weather, you predict, after pouring the concrete, you will have to wait 7 days before painting the water tower. This wait is an example of _____.
1. lags
2. leads
3. float
4. buffers
Answer and Explanation to
Yesterday's Question
Answer :
1. Fast-tracking or crashing, and inform the relevant stakeholders of the impact
of these actions.
-----------------------------------------------------------------------------------------------------------------------------
Question Explanation :
If the project schedule is delayed, you may use fast-tracking and crashing to determine whether the schedule can be shortened, while the manager has to be notified the impacts brought about by these techniques, such as increased cost and risks.
Source of Answer : PMBOK Guide,3rd, pages : 145-146