330. As a project manager, what can you do with the application of activity list?
1. To ensure project team members understand how to perform and complete the
work required.
2. To provide inputs for WBS.
3. To ensure project team members can understand the project scope.
4. To assist you to create technique documentation.
Answer and Explanation to
Yesterday's Question
Answer :
1. The process is to verify that the deliverables are accepted and
approved by the client and provide a chance to take different viewpoints.
-----------------------------------------------------------------------------------------------------------------------------
Question Explanation :
Scope verification is to obtain the stakeholder's formal acceptance on the completed project scope and related deliverables. Output of the scope verification includes: accepted deliverables, requested changes and recommended corrective actions.
Source of Answer :PMBOK Guide,3rd, pages : 118-119