Question of the Day #319

 

318. You are working on a large software development plan, comprising of multiple projects, and you find the outputs of these projects have a sequence. What should you do NEXT?

 


1. Obtain every product's project charter.

2. Obtain the WBS and management plan for each project.

3. Check that the project team members understand what they should do.

4. Check that every stakeholder understands the sequence of the project's outputs.

 







 

 



 

 

 

 

 

 

 

 

 

 

 


Answer and Explanation to Yesterday's Question


Answer :
1. Historical information


-----------------------------------------------------------------------------------------------------------------------------

Question Explanation :

When performing project planning, historical information is crucial. Please note that, though there appears the word "stakeholder" in the question, this is not an example of stakeholder analysis. Neither does it belong to scope management.

 

 

Source of Answer : 

 

For more of PMP's sharing, & Lessons Learned,  please visit http://www.pmsuccess.biz!