Task A is worth $400, is 95% complete, and
actually cost $395. Task B is worth $350, is
90% complete, and actually cost $330 so far. Task C is worth $275, is
100% complete, and has cost
$310 so far. The total budget is $2500. What is the
Variance at Completion for the tasks listed?
(a) -$168.09 (b) $2500 (c) $2668.09 (d) $1633.09 |
||||
|
Budget At Completion (BAC)
Total project budget; amount of money planned to be spent by the time the project is complete |
||
|
Crosswind Custom
Websites is building an ecommerce system. However, conflicting
priorities from other projects
has delayed the finish by two weeks. The schedule shows
that the next task is to define the requirements
needed by the customer, then that is followed by the
coding. This is an example of what?
(a) Mandatory Dependencies (Correct) (b) Lag (c) Discretionary Dependencies (d) Crashing Explanation: A mandatory dependency is required and internal to the organization. The discretionary dependency is a dependency that the Project Manager can utilize options in completing or working with. Crashing and Lag are noise in this question. For more questions, terminology and other exercises please see the PMP® Exam Success Series: Certification Exam Manual at www.c rosswind pm.com |